prima:Energy Bureau found that GeneraPR “misrepresented” project costs to acquire fast response generation units

The deadline for the projects for the acquisition of the units for three power plants will expire in the spring of 2026. Incidentally, the agency decided not to fine the consortium

September 18, 2024 - 4:09 PM

Archival note
This content was published more than 3 months ago.
The Energy Bureau ordered GeneraPR to complete the project for the acquisition of emergency peaking generation systems for the Jobos, Daguao and Palo Seco reservoir units by the end of spring 2026. (Xavier Araújo)

The Puerto Rico Energy Bureau (PREB) determined on Tuesday that the delays and increased costs of the project to acquire backup power generation units for the Jobos, Daguao and Palo Seco plants were the result of misrepresentations by the GeneraPR consortium.