prima:Federal program to install solar panels for vulnerable families will take up to five years

Funding allocated for the initiative -which will cover nearly 40,000 solar and battery storage systems- totals over $453 million

December 2, 2023 - 2:18 PM

Archival note
This content was published more than 1 year ago.
Agustín Carbó, director of the Puerto Rico Grid Recovery and Modernization Team (Suministrada)

The installation phase of up to 40,000 solar systems on vulnerable households in Puerto Rico could take nearly five years beginning in the spring of 2024. The U.S. Department of Energy (DOE) anticipates outreach to eligible households will begin in early 2024, and the first installations to begin in spring 2024.