prima:Obstacles to Completing Large-Scale Renewable Energy Projects Persist

Last month, developers and LUMA Energy only reached one of the six interconnection agreements pending

November 7, 2023 - 3:49 PM

Archival note
This content was published more than 1 year ago.
Since October 1, the 24-month clock has been ticking for the nine contractors to build the plants and have them ready to deliver energy to the grid (Archivo)

The deadline set by the Puerto Rico Electric Power Authority (PREPA), LUMA Energy and private developers to reach interconnection agreements for nine large-scale renewable energy projects expired on October 31 without most of the agreements necessary for the construction of the solar farms having been reached.